Home National Chattogram waterlogging project 92pc complete, full handover planned from April

Chattogram waterlogging project 92pc complete, full handover planned from April

by deskreport

The waterlogging mitigation project in Chattogram is nearing completion, with more than 92 percent of the work finished and a roadmap in place to complete the remaining tasks by March 2027.

The handover process from the Bangladesh Army’s 34 Engineer Construction Brigade to the Chattogram City Corporation (CCC) is scheduled to begin in April 2027. The project’s duration has been extended until June 2027, according to the brigade.

Lieutenant Colonel Mohammad Mohsinul Haque Chowdhury, project director of the 34 Engineer Construction Brigade, said he presented the roadmap at a consultative meeting held at the CCC office on September 23. Representatives of different service-providing agencies attended the meeting to discuss measures to address waterlogging in the port city.

“Over 92 percent of the project work is already complete, and contractors are working at full pace to finish the rest,” he said.

He expects the remaining work to be completed by the last week of March, with the handover process beginning in early April.

Following completion, the Chattogram Development Authority (CDA) will start transferring project responsibilities to the CCC. The process will include sharing technical knowledge and providing training on maintenance before the city corporation assumes full responsibility.

Focus on maintenance and coordination

The government has stressed the importance of proper maintenance after project completion and ensuring effective connections among canals, drains and the wider drainage network.

At the September meeting, Water Resources Minister Shahiduddin Chowdhury Annie emphasised the need to consider long-term maintenance and operation while planning infrastructure projects.

“Building infrastructure is not enough,” he said, adding that authorities must consider how projects would be operated and maintained, how water would flow and how canals and drains could function as an interconnected system.

The minister acknowledged that earlier planning had lacked an integrated approach, prompting agencies to improve coordination.

“Rather than dwelling on the limitations of the past, we must focus on making existing infrastructure effective and sustainable,” he said, stressing that the activities of one organisation should not remain disconnected from those of others.

Work on 36 canals nearing completion

Project Director Mohammad Mohsinul Haque Chowdhury said work on 30 of the project’s 36 canals had been completed.

Work on the remaining six canals is 98 percent complete, although some finishing tasks were delayed by the early arrival of the monsoon. Those activities are now underway and are expected to be completed by December.

Excavation of the Hijra Canal, which was suspended during the monsoon, has also resumed.

The remaining retaining walls, bridges and three silt traps are scheduled for completion by March 2027.

The project director said the brigade would share technical knowledge and practical experience gained over the past eight years during the handover process.

This would include informing the CCC about challenges encountered while renovating different canals, identifying the equipment required for future maintenance and explaining how to operate it.

The brigade will also provide guidance on maintaining and repairing regulators, including their operation and routine inspection.

He said the city corporation would take full responsibility once all formalities were completed and the handover process finished.

The brigade has already submitted a proposal to the CCC, he added. If the corporation needs a year or more to prepare for maintenance, it should immediately prepare a Detailed Project Proposal (DPP) and seek approval from the relevant ministry.

Measures to protect canals

The project has included retaining walls to prevent future encroachment by permanently marking canal boundaries.

Service roads are also being constructed alongside the canals to allow modern machinery, including excavators and dump trucks, to reach the waterways for cleaning and debris removal.

Trees will be planted along these roads to improve the city’s appearance and create spaces for residents to enjoy evening walks.

Regarding the proposed handover, CCC Administrator Dr Shahadat Hossain said the CDA had expressed interest several times in transferring the project to the city corporation.

However, he said the CCC would take responsibility for maintenance only after all project work had been completed.

“The CDA recently asked us to take over the project once it is finished. We are considering this and will decide how to proceed with addressing waterlogging in the future,” he said.

The Executive Committee of the National Economic Council (ECNEC) approved the CDA project, titled “Re-excavation, Expansion, Renovation, and Development of Canals for Waterlogging Mitigation in Chattogram City”, on August 9, 2017, at an estimated cost of Tk 5,616 crore.

The project was initially scheduled for completion within three years, ending in 2020.